Vice Chairman of the Provincial People's Committee Nguyen Le Huy works with the National Power Transmission Corporation

On the morning of August 8, Comrade Nguyen Le Huy, Member of the Provincial Party Committee’s Standing Board, Vice Chairman of the Provincial People's Committee chaired a working session with the National Power Transmission Corporation (EVNNPT) led by Comrade Pham Le Phu, General Director of EVNNPT at the Headquarters of the Provincial People's Council and the Provincial People's Committee.

Delegates attend the working session.

Speaking at the working session, EVNNPT General Director Pham Le Phu said that EVNNPT hopes to remove difficulties and obstacles for a number of grid development projects that the Corporation is implementing in the province.

Comrade Pham Le Phu, General Director of EVNNPT, speaks at the working session.

Delegates listened to a report on the investment situation of the electricity sector in the province in the past time. Accordingly, EVNNPT is currently investing in the following projects: 500kV Hai Phong - Thai Binh line; 500kV Thai Binh transformer station; 500kV Hung Yen 1 substation and 500kV, 220kV connecting lines; 220kV Thai Binh - Thanh Nghi line; 220kV Bai Say substation, 220kV Bai Say - Kim Dong line.

Comrade Nguyen Le Huy, Member of the Provincial Party Committee’s Standing Board, Vice Chairman of the Provincial People's Committee, delivers a speech at the meeting.

At the meeting, Vice Chairman of the Provincial People's Committee Nguyen Le Huy requested departments, branches and localities to clarify a number of issues that EVNNPT is concerned about such as: A number of projects facing difficulties and obstacles related to site clearance; adjusting the route of the 500kV Hai Phong - Thai Binh line; the locations for dumping excess soil and rock during construction.

In his concluding remarks, Vice Chairman of the Provincial People's Committee Nguyen Le Huy acknowledged the contributions of the electricity sector to the province's development in recent times. Given the increasing speed of development and demand for electricity, the investment in power transmission projects is essential. He requested departments, branches, sectors and localities to continue to closely coordinate with investors, promptly remove difficulties and obstacles, and ensure project progress. In particular, site clearance work needs to be focused on and strives to be completed in August 2025. At the same time, EVNNPT is requested to send staff to coordinate directly with commune authorities to speed up the progress of inventory and compensation. Immediately after the site is handed over, it is necessary to mobilize construction forces quickly to avoid new problems.

Source: baohungyen.vn

How satisfied are you with the information in this article?

Satisfaction level

No personal data is collected. Each article can be rated once per day.


Administrative map

Satisfaction rating

How satisfied are you with the information on this portal?

Your feedback helps us serve you better.

USER FEEDBACK

Rating results

Satisfaction with the information provided

88ratings recorded
Very satisfied33%
29 ratings
Satisfied28%
25 ratings
Neutral30%
26 ratings
Dissatisfied0%
0 ratings
Other9%
8 ratings
Thank you for your feedback!
Visits2,256,153Total visits
Online now22
Visits today1,169

Online: active in the last 5 minutes