The Provincial People's Committee reviews the progresses of public investment projects and capital disbursement
On the morning of August 13, the Provincial People's Committee held a meeting with the Construction Investment Project Management Board No. 01 to review the implementation status of public investment projects and the disbursement of public investment funds. Mr. Lai Van Hoan, Member of the Provincial Party Committee and Vice Chairman of the Provincial People's Committee, presided over the meeting.
According to the report, the Construction Investment Project Management Board No. 01 is currently implementing 71 projects: 46 projects are under construction, 16 projects are in the project preparation phase, and 9 projects are in the stage of preparing reports to propose investment policies.
For the year 2026, the Board was assigned a capital plan of approximately VND 10,300 billion for 59 projects. As of August 11, approximately VND 4,558 billion has been disbursed, reaching 44.3% of the plan. The Board aims to disburse approximately VND 5,271 billion (51.2%) by the end of August, reach approximately VND 9,319 billion (90.6%) by year-end, and complete 100% of the plan by January 2027.
At the meeting, the Construction Investment Project Management Board No. 01, and relevant departments, agencies, and localities, reported on the construction and site clearance progress of each project while highlighting existing difficulties and obstacles. Several projects are facing significant site clearance issues; for instance, the Ring Road No. 3.5 section from the provincial road No. 378 to National Highway No. 5 still has 8.1 out of 8.4 km pending clearance; the provincial road No. 387 has 3.2 out of 7.2 km pending; and the provincial road No. 382B has 3.8 out of 17.9 km pending.
Leader of the Construction Investment Project Management Board No. 01 speaks at the meeting.
Leader of the Department of Construction speaks at the meeting.

Local leader discusses at the meeting.
In his concluding remarks, Vice Chairman of the Provincial People's Committee Lai Van Hoan acknowledged that while progress on key transport projects and public investment capital disbursement has improved, it remains slower than required. He urged departments, agencies, the Construction Investment Project Management Board No. 01, and the commune/ward People's Committees to focus intensely and take decisive action to accelerate disbursement; he emphasized that site clearance is a priority task linked to the accountability of the heads of these units.
Vice Chairman of the Provincial People's Committee Lai Van Hoan delivers directives at the meeting.
The Vice Chairman of the Provincial People's Committee instructed the Construction Investment Project Management Board No. 01 to urge contractors to proactively arrange materials, equipment, and personnel, and organize continuous construction work; he directed them to coordinate with relevant units to resolve material supply issues and prevent construction interruptions.
Regarding site clearance, he requested that the commune and ward People's Committees strictly adhere to the milestones agreed upon by the Provincial People's Committee and urgently hand over agricultural land for construction; remaining tasks must be completed on schedule, avoiding the setting of merely perfunctory deadlines.
He directed departments, agencies, and localities to focus on decisively resolving bottlenecks affecting key projects, such as the provincial road No. 387 and the provincial road No. 382B; the road and embankment along the Ban River; the Chi Tan - Toan Thang route; the planned 69-meter-wide Pham Ngu Lao road passing through Duc Hoa Industrial Park; the East-West road; roads 384 and 382; and Ring Road No. 3.5. Particular focus must be placed on the East-West road and Ring Road No. 3.5; this entails regular site inspections and the immediate resolution of any outstanding issues to ensure the progress of these key provincial projects and the achievement of the 2026 public investment disbursement targets.