Vice Chairman of the Provincial People's Committee Nguyen Hung Nam inspects the progress of the investment project to build the Ring Road No. 4 - Hanoi Capital Region

On the morning of July 17, Vice Chairman of the Provincial People's Committee Nguyen Hung Nam inspected the progress of the investment project to build the Ring Road No. 4 - Hanoi Capital Region, the section passing through the province.

Vice Chairman of the Provincial People's Committee Nguyen Hung Nam inspects the project site.

According to the investor's report, up to now, the total area of land clearance of the project is 210.58 hectares, reaching 93.24% of the total area of land that needs to be recovered. Regarding residential land, localities have completed the work of counting and determining the origin of the land; basically completed the plan for compensation and support for residential land; currently, the compensation plan, support for residential land and resettlement plan are being publicized and finalized; a number of localities have approved the plan and issued decisions to reclaim residential land. The construction unit has completed about 52.66% of the contract value...

Vice Chairman of the Provincial People's Committee Nguyen Hung Nam directs at the inspection session.

Inspecting the actual situation at the site, Vice Chairman of the Provincial People's Committee Nguyen Hung Nam requested localities to mobilize resources and focus on performing well the work of land acquisition for residential land. In particular, urgently publicize the compensation plan and resettlement arrangement for households. To focus on propagating and mobilizing people to understand the purpose, meaning and benefits of the project, creating high consensus in handing over the site, creating favorable conditions for the construction unit. Departments and branches guide localities on compensation procedures, support for site clearance, resettlement arrangements, etc. Construction units mobilize maximum machinery, equipment, and human resources, command the construction teams to coordinate smoothly, speed up construction progress of sections with cleared land. Investors strengthen inspection and supervision work, ensure progress and quality of works, etc.

Source: baohungyen.vn

How satisfied are you with the information in this article?

Satisfaction level

No personal data is collected. Each article can be rated once per day.


Administrative map

Satisfaction rating

How satisfied are you with the information on this portal?

Your feedback helps us serve you better.

USER FEEDBACK

Rating results

Satisfaction with the information provided

87ratings recorded
Very satisfied32%
28 ratings
Satisfied29%
25 ratings
Neutral30%
26 ratings
Dissatisfied0%
0 ratings
Other9%
8 ratings
Thank you for your feedback!
Visits2,172,367Total visits
Online now76
Visits today2,959

Online: active in the last 5 minutes