The Provincial People's Committee reviews the progress of projects scheduled to commence in 2026
On the afternoon of August 13, Mr. Nguyen Manh Quyen—Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee—chaired a meeting to hear the Department of Finance report on the progress, roadmap, and schedules for the projects slated to begin around the National Day September 2nd and throughout 2026, as well as to address any obstacles hindering them.
Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, chairs the meeting.
The meeting drew the attendance of Mr. Nguyen Hung Nam and Mr. Lai Van Hoan (Members of the Provincial Party Committee and Vice Chairmen of the Provincial People's Committee); Mr. Vu Thanh Van, Member of the Provincial Party Committee’s Standing Board and Director of the Department of Industry and Trade; and leaders of relevant departments and agencies.
According to the Department of Finance's report, a review identified 22 public investment projects scheduled to commence in 2026. Among them, the project to construct frontage roads and overpasses along the route connecting cultural-tourism heritage sites and fostering economic development along the Red River is set to begin around the National Day September 2nd. Additionally, two industrial zone infrastructure projects and one industrial cluster infrastructure project are supposed to commence during the same holiday period.
Provincial leaders and delegates attend the meeting.
Mr. Vu Thanh Van, Director of the Department of Industry and Trade, presents a report at the meeting.
Leader of the Department of Construction presents a report at the meeting.
Leader of the Construction Investment Project Management Board No. 01 presents a report at the meeting.
Provincial leaders and delegates attend the meeting.
At the meeting, delegates discussed and clarified matters regarding the roadmap and commencement schedules for the projects; while proposing solutions to resolve difficulties and obstacles to ensure the projects commence according to schedule.
In his concluding remarks, Mr. Nguyen Manh Quyen—Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee—directed departments, agencies, and units to continue reviewing and assessing the list of projects scheduled to launch during the National Day September 2nd and the final months of 2026. He urged them to strive to complete all procedures and break ground on six industrial park infrastructure projects and at least two industrial cluster infrastructure projects by the September 2nd and prior to the planned mid-September 2026 conference to announce the adjusted provincial master plan, unveil the province's logo and anthem, and promote investment in the province.
The Chairman of the Provincial People's Committee required the development of critical path schedules for completing investment procedures for each specific project and the assignment of clear tasks to relevant departments, agencies, units, and localities. He emphasized the need for proactive coordination, guidance, and problem-solving within their respective jurisdictions, upholding the spirit of a facilitating government that actively serves businesses and the public.
He tasked the Department of Agriculture and Environment with accelerating support for project investors in finalizing environmental and land allocation procedures, and directed the Provincial Public Security to assist investors in completing fire prevention and safety documentation. Local authorities were instructed to coordinate with investors to definitively complete site clearance.
At the meeting, the Chairman of the Provincial People's Committee assigned the Vice Chairmen of the Provincial People's Committee to proactively review and monitor progress, ensuring projects are carried out on schedule and with yield high results, thereby contributing to the province's economic growth.