The Provincial People's Committee reviews and provides feedback on industrial cluster development

On the morning of August 4, Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, presided over a meeting to hear a report of the Department of Industry and Trade, which covered the development status and technical infrastructure investment for industrial clusters (ICs) in the province; the results regarding planning, establishment, site clearance, infrastructure investment, and investment attraction; as well as challenges and proposed solutions; the feedback provided on the draft Regulation on IC management and the IC development plan of Hung Yen province for the 2026–2030 period.

Delegates attend the meeting.

In the attendance were Mr. Vu Thanh Van, Member of the Provincial Party Committee’s Standing Board and Director of the Department of Industry and Trade, leaders of provincial departments, agencies, localities, and IC infrastructure investors.

Leaders of departments, agencies, localities, and IC investment enterprises attend the meeting.

According to the Department of Industry and Trade's report, the province has planned for 115 ICs covering a total area of ​​approximately 7,319.76 hectares. In the first seven months of 2026, the Department has advised the Provincial People's Committee to issue decisions establishing four new ICs, bringing the total number of established clusters to 86 Ics with a combined area of ​​about 4,668.38 hectares. Additionally, the establishment decisions for 21 clusters have been amended, creating the foundation for technical infrastructure construction and the attraction of secondary investors.

Mr. Vu Thanh Van, Director of the Department of Industry and Trade, reports at the meeting.

To date, 80 out of 86 ICs have had their detailed construction plans or zoning plans approved; 19 ICs have completed site clearance, 45 ICs are currently undergoing site clearance, and 22 ICs are carrying out procedures to prepare for site clearance. During the first seven months of the year, the area cleared for development reached 550.55 hectares, representing 91.8% of the initial annual target; the area developed with technical infrastructure reached 330 hectares, exceeding the plan by 10%, bringing the total infrastructure-equipped area to 1,573.81 hectares. Currently, 16 industrial clusters have essentially completed their technical infrastructure, 48 clusters are under construction, and 22 clusters are finalizing procedures to launch their projects.

Concurrently, investment attraction efforts have yielded positive results. To date, 49 industrial clusters have attracted 548 secondary investment projects, comprising 461 domestic projects and 87 foreign direct investment (FDI) projects, with a total registered capital of VND 49,839.4 billion and USD 1,547.9 million.

At the meeting, building upon the points raised by the Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, delegates analyzed the causes of existing shortcomings and limitations. They provided feedback on the draft regulations for industrial cluster management and the development plan of Hung Yen Province's industrial clusters for the 2026–2030 period. Furthermore, they proposed solutions to accelerate site clearance and infrastructure completion, enhance investment attraction efficiency, and review development plans to ensure alignment with the provincial master plan and the requirements of the new development phase.

Leader of the Provincial Public Security speaks at the meeting.

Leader of the Department of Construction speaks at the meeting.

Representative of enterprises and industrial cluster infrastructure investors discusses at the meeting.

The proposals falling within their jurisdiction were addressed and clarified by the Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, as well as leaders of relevant departments and agencies. The remaining issues have been assigned to relevant agencies to review, study, and advise the Provincial People's Committee on appropriate resolution in accordance with regulations.

In his concluding remarks, Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, directed the Department of Industry and Trade to take the lead in coordinating with other departments, sectors, and localities to review the planning of industrial clusters across the province. He instructed them to promptly propose adding new clusters to the master plan if it is necessary and consider establishing one or two clusters specifically designated for projects with potential environmental pollution risks.

Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, delivers directives at the meeting.

Regarding industrial clusters already in operation, he required a review to ensure compliance with approved plans and issued permits, as well as to guarantee adequate environmental treatment and fire prevention and fighting infrastructure. For clusters currently under development, he urged local Party committees and authorities to accelerate site clearance progress and called on project investors to speed up technical infrastructure construction to be ready to attract secondary investors.

The Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee requested the Department of Construction to accelerate the implementation of social housing and rental housing projects to meet the housing needs of workers and laborers. He directed the Department of Home Affairs to carry out solutions for attracting, training, and upskilling the workforce to meet labor demands in the province's industrial zones and clusters.

Acknowledging the feedback and proposals from businesses, the Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee assigned the Department of Industry and Trade to compile the information and propose courses of action. He urged businesses and investors to uphold their sense of responsibility, demonstrate professionalism and credibility, and carry out industrial cluster investments in strict accordance with approved plans, schedules, and commitments. At the same time, it is affirmed that Hung Yen province would continue to accelerate reforms, simplify procedures, and provide maximum support to enterprises investing in industrial cluster infrastructure as well as to secondary investors.

Tat Dat

How satisfied are you with the information in this article?

Satisfaction level

No personal data is collected. Each article can be rated once per day.


Administrative map

Satisfaction rating

How satisfied are you with the information on this portal?

Your feedback helps us serve you better.

USER FEEDBACK

Rating results

Satisfaction with the information provided

87ratings recorded
Very satisfied32%
28 ratings
Satisfied29%
25 ratings
Neutral30%
26 ratings
Dissatisfied0%
0 ratings
Other9%
8 ratings
Thank you for your feedback!
Visits2,172,303Total visits
Online now15
Visits today2,895

Online: active in the last 5 minutes