The Provincial People's Committee holds a meeting to hear reports on the progress of several projects in the province.
On the afternoon of May 14, Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, chaired a meeting of the Provincial People's Committee to hear reports of departments, agencies, and localities on the progress of several projects in the province. The meeting saw the participation of members of the Provincial Party Committee’s Standing Board, leaders of the Provincial People's Committee; leaders of relevant departments, agencies, localities, and businesses.
Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, chairs the meeting.
At the meeting, leaders of departments, agencies, localities, and contractors reported on the progress of the following projects: the PVF Youth Football Training Center project; the connecting roads to the PVF stadium area; the mixed-use urban area in Nghia Tru - Van Giang - Hoan Long communes; the Van Giang Industrial Park - Phase I; and the adjustment of the construction planning for sub-area E1, Van Giang urban area.
According to the report, the PVF Youth Football Training Center project is being implemented on an area of approximately 92.2 hectares in Nghia Tru and Van Giang communes, with a total investment of over 2,051 billion VND. To date, phase 1 of the project has completed construction and is operational. For the expansion in phase 2, covering approximately 71.89 hectares, the land clearance has been 100% completed. Currently, the investor is carrying out land procedures to obtain land allocation and land lease according to regulations.
The transportation projects connecting to the PVF stadium area include: the investment project to build the East-West arterial road I (the section from the provincial road No. 378B to provincial road No. 382B); the extended Thanh Nien road to the district road No. 26; the extended Thanh Nien road from the district road No. 26 to the provincial road No. 377; and the extended Thanh Nien road from the provincial road No. 377 to the Ring Road No. 4. Regarding the investment project to build a connecting road from the provincial road No. 378 to the provincial road No. 382B; and the investment project to build a road alongside the provincial road No. 379 from the Ring Road 3.5 to the National Highway No. 39 overpass, local authorities are focusing on land clearance, constructing resettlement areas, completing land acquisition documents, inventorying assets on the land, and paying compensation and support to affected households. Several key projects such as the East-West road I, the extended Thanh Nien road, and the connecting road from the provincial road No. 378 to the provincial road No. 382B are being accelerated.
The mixed-use urban area project in Nghia Tru, Van Giang, and Hoan Long communes covers an area of approximately 171.8 hectares with a total investment of approximately 21,000 billion VND. Currently, the Department of Construction is carrying out procedures related to selecting a consulting contractor and organizing the selection of investors according to regulations.
The Van Giang Industrial Park Project - Phase I requires land acquisition of approximately 273 hectares, located in Nghia Tru commune. To date, the local authorities have completed the review and land ownership assessment for 100% of the area; and issued land acquisition notices for approximately 110 hectares.
Regarding the adjustment of the construction planning for sub-area E1 of the Van Giang urban area, the Department of Construction and related units are currently gathering opinions from departments, agencies, localities, and the community to finalize the dossier for submission to the Provincial People's Committee for consideration and approval according to regulations.
At the meeting, delegates focused on discussing and clarifying difficulties and obstacles, especially in land clearance and investment procedures; and simultaneously proposed solutions to accelerate the progress of the projects.
Leader of the Provincial Industrial Parks Management Board speaks at the meeting.
Leader of the Investment and Construction Project Management Board No. 01 speaks at the meeting.
Leader of Van Giang commune speaks at the meeting.
A representative of the investor speaks at the meeting.
Concluding the meeting, Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, assessed that the progress of some projects had not met the set requirements; he also requested that departments, localities, and investors make efforts to overcome difficulties, strengthen coordination, and focus on accelerating the implementation of the work contents of each project.
Mr. Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, gives directives at the meeting.
He requested the urgent completion of land allocation for the PVF Youth Football Training Center project. Regarding the roads connecting to the PVF stadium area, he urged the acceleration of land clearance, resettlement, and temporary housing; contractors should begin construction wherever land is available, striving to complete all connecting transportation projects before March 2027.
Regarding the mixed-use urban development project in Nghia Tru, Van Giang, and Hoan Long communes, the Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee requested that relevant departments, agencies, and localities urgently complete all related procedures, striving to finalize the investor selection before July 15, 2026.
Regarding the adjustment of the construction planning for sub-area E1 of the Van Giang urban area, he requested research and supplementation of the planning for commercial and service areas associated with the PVF stadium complex. For the Van Giang Industrial Park - Phase I project, Nghia Tru commune needs to flexibly implement solutions, strengthen propaganda and mobilization efforts to gain people's consent to hand over the land. Relevant departments and agencies should increase the number of professional staff to support the locality in land acquisition work, ensuring the timely handover of land to the investor.
Comrade Nguyen Manh Quyen, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, instructed departments, agencies, and local units to ensure that the project implementation steps are carried out strictly, openly, transparently, and in accordance with the law. Investors need to focus resources and implement the project on schedule, ensuring the quality and aesthetics of the construction.