The Provincial People's Committee holds a meeting to hear reports on the progress of key transport projects
On the afternoon of August 8, the Provincial People's Committee held a meeting to hear the Construction Investment Project Management Board No. 2 report on the progress of implementation and site clearance of a number of key transport projects and works in the province. Comrade Nguyen Khac Than, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee chaired the meeting. The meeting drew the attendance of Comrade Nguyen Quang Hung, Member of the Provincial Party Committee’s Standing Board, Standing Vice Chairman of the Provincial People's Committee; leaders of relevant departments, branches, units and localities.
Delegates attend the meeting.
According to the Construction Investment Project Management Board No. 2, there are currently three key transport projects being implemented in the area, including the project to invest in the construction of the Ninh Binh - Hai Phong expressway, the section through Nam Dinh (old) and Thai Binh (old) provinces under the PPP form, which has so far completed the site clearance of about 360.8/395.68 hectares of agricultural land (reaching 91%), of which Hung Yen province reached 97%, Ninh Binh province reached 84%. Localities have handed over about 82% of the rice land to investors. The investor consortium has completed mine clearance and appraised a number of large bridge items. Regarding the disbursement of public investment capital, the project is allocated from the central budget of 5,700 billion VND (this source of capital has not yet been disbursed). In addition, Hung Yen province has allocated VND561.123 billion, of which VND388.334 billion has been disbursed and VND130 billion of loans from the Provincial Land Fund Development Center have been disbursed; Ninh Binh province has allocated VND1,000 billion, of which VND312.52 billion has been disbursed.
The project to invest in the construction of a road from Thai Binh city (old) to Hung Ha connecting with Hung Yen has a length of 24.8km with a total investment of VND4,928 billion. Up to now, the project has completed the survey and design tasks, is selecting a consulting contractor; at the same time, it is preparing to stake out the site clearance and hand over the road boundary markers.
The project to invest in the construction of a road connecting Thai Binh city (old) to Nghin bridge under the form of public investment has a length of 21.28km, with a total investment of VND2,121 billion. Up to now, the investor has signed contracts with construction contractors and supervision consultants; is filling the foundation, completing procedures, and receiving items from the PPP project.
At the meeting, leaders of departments, branches, localities and investors focused on discussing and analyzing difficulties and problems related to land clearance, resettlement, relocation of related technical infrastructure, material sources, etc.; at the same time, discussing solutions to help remove bottlenecks, speeding up the implementation of projects in the coming time.
Concluding the meeting, Chairman of the Provincial People's Committee Nguyen Khac Than emphasized: These are all important transport projects, connecting regions and creating development space for the province. Therefore, in the process of project implementation, departments, branches and localities need to clearly define responsibilities, determination, and clearly define the completion time.
Comrade Chairman of the Provincial People's Committee Nguyen Khac Than speaks at the meeting.
The Chairman of the Provincial People's Committee also frankly pointed out a number of shortcomings that have prevented projects from being implemented as expected, including objective reasons. He requested that departments, branches and localities have flexible leadership, direction and coordination methods in removing difficulties and obstacles for each specific project.
For the investment project to build the road connecting Thai Binh city (old) to Nghin bridge under the form of public investment, it must be determined to complete it in 2026, in which the section from Nghin bridge to the district road No.72 strives to be completed in November 2025; the section from Vo Nguyen Giap street to National Highway No. 39A is expected to be completed before Tet holiday 2026.
For the investment project to build the Ninh Binh - Hai Phong expressway, the section through Nam Dinh province (old) and Thai Binh province (old) under the form of PPP, the province continues to highly agree with the Prime Minister's direction; at the same time, focuses on accelerating the project progress according to the motto of speed, determination, "3 shifts, 4 teams", working through holidays and Tet to ensure the set progress...
For the investment project to build the road from Thai Binh city (old) to Hung Ha connecting with Hung Yen, the project started construction to welcome the Congress of Hung Yen Provincial Party Committee for the term 2025 - 2030, striving to complete the target in the second quarter of 2027.
The Chairman of the Provincial People's Committee requested that immediately after the meeting, the Investment Project Management Board No. 2 coordinate with related localities and investors to build specific progress curve for each project with the most drastic, determined and urgent viewpoint and determine that this is the basis for checking and monitoring the progress of the projects. The implementation process ensures that the tasks and parts of the work are carried out simultaneously, flexibly, without waiting or mechanically. In the current period, departments, branches and localities are focusing on site clearance, resettlement arrangements...
The Chairman of the Provincial People's Committee assigned the Department of Agriculture and Environment to advise on the solutions to remove difficulties in the source of materials for leveling and construction of projects, in which priority is given to the source of materials supplied to key works and projects of the province. The Department of Construction focuses on monitoring, supervising and urging the progress of project implementation. The Department of Finance advises on the allocation of resources to carry out projects. The Construction Investment Project Management Board No. 2 and the Land Fund Development Center No. 2 regularly grasp difficulties and obstacles in project implementation, especially in site clearance work, to promptly remove them and speed up construction progress.
The Party Secretaries and Chairmen of the People's Committees of communes and wards promote their roles and responsibilities, closely coordinate with relevant departments, branches and units to boost propaganda work, creating consensus among people in the project area.