The Provincial People's Committee holds a meeting on the progress of the implementation of key projects

On the morning of September 9, the Provincial People's Committee held a meeting to hear reports from units on the progress of implementation of key projects in the province. Comrade Nguyen Quang Hung, Member of the Provincial Party Committee’s Standing Board, Standing Vice Chairman of the Provincial People's Committee chaired the meeting. In the attendance were relevant departments, branches, sectors and localities.

Delegates attend the meeting

According to the Report of the Construction Investment Project Management Board No. 2, the Ninh Binh - Hai Phong Expressway construction investment project, the section through Nam Dinh and Thai Binh under the PPP method, the section through Hung Yen (CT.08) has so far cleared more than 203 hectares, reaching 98.6% of the area, and handed over the scope of agricultural land, traffic land, irrigation land corresponding to more than 31km, reaching 93.7%. The residential and resettlement land is being carried out and expected to be completed in 2026.

For the investment project to build a road from Thai Binh ward through Hung Ha commune connecting with Pho Hien ward, the Construction Investment Project Management Board No. 2 is urgently conducting investment procedures, ensuring the conditions for the expected commencement of construction in October 2025.

The Thai Binh LNG Thermal Power Plant project with a capacity of 1,500 MW is basically following the schedule. By the end of August 2025, the investor has paid about 67 billion VND for site clearance compensation. For the floating and submerged storage system, the Ministry of Construction and the Vietnam Maritime and Waterway Administration have agreed on the location and technical specifications. The Provincial People's Committee has sent a document to the Ministry of Industry and Trade and the Vietnam Electricity Group, requesting the National Power Transmission Corporation to be the investor of two 220kV transmission lines connecting the project.

VSIP Thai Binh Industrial Park Project has completed site clearance of more than 253 hectares by the end of August 2025, of which nearly 236 hectares have been handed over to investors. The area of ​​infrastructure construction covered 12 hectares, expected to increase to 50 hectares in 2025. The cleared land fund ready for lease is currently about 10 hectares.

At the meeting, delegates focused on discussing solutions to remove difficulties and obstacles to speed up the progress of project implementation.

Concluding the meeting, Mr. Nguyen Quang Hung, Standing Vice Chairman of the Provincial People's Committee, emphasized that these are all key projects of the province in the current period to complete the regional transport infrastructure network as well as the new development space of the province. Therefore, all levels and sectors must identify this as an important political and professional task, prioritize attention, focus human resources and resources on site clearance. After receiving the land, investors must promptly organize construction to ensure the progress of the projects.

The Standing Vice Chairman of the Provincial People's Committee speaks at the meeting.

Regarding the CT.08 project, the section passing through Hung Yen province, the Standing Vice Chairman of the Provincial People's Committee requested that, based on the guidance of departments and branches, communes proactively study and develop plan for site clearance and compensation to seek opinions from relevant departments and branches. Regarding the implementation time and roadmap, by November at the latest, the area of ​​agricultural land and residential land with clearly identified land origin must be handed over; resettlement land, power lines, infrastructure works and some key locations on the route must be handed over in December 2025 or early January 2026. At the same time, urgently complete procedures related to the implementation of works affected by the CT.08 project so that enterprises can soon hand over the site to serve the construction of some items of the project.

For the investment project to build a road from Thai Binh ward through Hung Ha commune connecting with Pho Hien ward, he requested the Construction Investment Project Management Board No. 02 and the Land Fund Development Center No. 2 to urgently carry out site clearance; at the same time, develop a plan and implementation roadmap, strive to complete the entire route to put it into operation soon, in order to promote investment efficiency, contributing to boosting the socio-economic development of the province.

For the Thai Binh LNG Thermal Power Plant project, he requested the Management Board of Economic Zone and Industrial Parks of the province and localities to develop a plan to organize the project groundbreaking ceremony; coordinate to review and complete legal procedures related to the project.

The Standing Vice Chairman of the Provincial People's Committee also requested investors to coordinate with relevant departments and sectors to focus on resolving difficulties and problems related to the projects. Sectors and localities urgently coordinate and create conditions to remove difficulties, especially ensuring the supply of construction materials for the projects.

Tat Dat

How satisfied are you with the information in this article?

Satisfaction level

No personal data is collected. Each article can be rated once per day.


Administrative map

Satisfaction rating

How satisfied are you with the information on this portal?

Your feedback helps us serve you better.

USER FEEDBACK

Rating results

Satisfaction with the information provided

87ratings recorded
Very satisfied32%
28 ratings
Satisfied29%
25 ratings
Neutral30%
26 ratings
Dissatisfied0%
0 ratings
Other9%
8 ratings
Thank you for your feedback!
Visits2,172,323Total visits
Online now33
Visits today2,915

Online: active in the last 5 minutes