Hung Yen: Removing "bottlenecks" for key projects

In the whole province there are currently many key projects being implemented such as: the investment project to build the Ring Road No. 4 - Hanoi Capital Region; Tan Phuc - Vong Phan Road Project (intersecting with the provincial road No. 378); the investment project to build housing area for low-income people in Yen My II Industrial Park...

In which, Tan Phuc - Vong Phan Road Investment Project (intersecting with the provincial road No. 378) started construction in November 2023. During the implementation process, the project has encountered some difficulties in site clearance such as: the orders and procedures for supplementing land use planning take a long time; the compensation support for land acquisition and resettlement for residential land areas and resettlement arrangements have not yet ensured progress and plans...

With the determination to remove difficulties and obstacles, ensure project progress according to the direction of the Provincial Steering Committee for Key Projects for the period 2021-2025, which is to basically complete the project before September 30, 2025, in the past time, Party committees and authorities from the province to the grassroots have focused on removing each "bottleneck". In particular, the work of propagating and mobilizing people to strictly comply with the Party's guidelines, policies and laws of the State in the fields of land management, planning management, construction order to carry out compensation and site clearance is given top priority.

On April 29, 2025, the Provincial People's Committee issued Decision No. 1007/QD-UBND stipulating other support levels when the State reclaims land and clears the site to implement the Tan Phuc – Vong Phan road project (intersecting with the provincial road No. 378). This is considered an important decision of the province to remove difficulties in the project's site clearance work.

Accordingly, the Provincial People's Committee stipulates 7 main support groups when the State reclaims land and clears the site to implement the Tan Phuc - Vong Phan road project, typically: Support for house rent of 6 million VND/household/month for a maximum of 9 months for people whose residential land has not been resettled, have no other place to live or whose house has been demolished and cannot be used; Support for residential land for areas encroached upon by households and individuals, or for areas that have been converted to other purposes by themselves before July 1, 2014, if eligible for a Certificate of Land Use Rights before the planning and plans are issued but have not been granted, support equal to the compensation level for residential land, minus financial obligations according to regulations...

Mr. Tran Minh Hai, Director of the Management Board of Traffic Construction Investment Projects, said: The project has received close attention from the Provincial Party Committee, the Provincial People's Council, and the Provincial People's Committee, and has been identified as a key project to welcome the 20th Provincial Party Congress, term 2025 - 2030. Through propaganda and mobilization, households in the project area have basically agreed and supported the implementation of the project. Up to now, the investor has coordinated with the districts to hand over the construction site to the contractor to construct more than 97% of the area that needs to be recovered. The contractors are organizing 11 construction teams along the entire route to construct the project with an implementation value of over 1.1 trillion VND.

The construction of Dang Le Industrial Cluster infrastructure

The key industrial park and industrial cluster projects have been and are being implemented such as: Tho Hoang Industrial Park Infrastructure Investment and Construction Project; Kim Dong Industrial Cluster Project; Dang Le Industrial Cluster Project... are identified as breakthrough projects to realize the goal of turning Hung Yen into a modern industrial province. With the efforts of the entire political system, the investment and construction of infrastructure for industrial parks and industrial clusters in the province have achieved a lot of positive results. In particular, the Tho Hoang Industrial Park Infrastructure Investment and Construction Project has been approved by the Provincial People's Committee for the task and estimate of the construction planning at a scale of 1/2000 on March 12, 2025 and the Plan for selecting contractors for the planning project was approved on April 8, 2025. The Kim Dong Industrial Cluster project has cleared nearly 93% of the construction site... Mr. Vu Quoc Nghi, Head of the Provincial Industrial Park Management Board, said: The province's consistent guiding viewpoint for sectors and localities is to ensure favorable conditions for businesses to build technical infrastructure in industrial parks and industrial clusters; how to always have cleared land and adequate infrastructure to attract investors. Up to now, the implementation of many key industrial park and industrial cluster projects has changed positively.

Mr. Nguyen Duc Tai, Director of the Department of Finance, said: The key projects of the province being implemented are important projects to promote the socio-economic development of the province. With the strong direction of the Provincial Party Committee and the Provincial People's Committee, many key projects of the province are being performed by all levels and sectors. However, the progress of some projects is slower than required. Therefore, in the coming time, all levels, sectors and localities need to take more drastic measures in implementing procedures related to investment, land, site clearance and compensation, ensuring the progress of project implementation.

Source: baohungyen.vn

How satisfied are you with the information in this article?

Satisfaction level

No personal data is collected. Each article can be rated once per day.


Administrative map

Satisfaction rating

How satisfied are you with the information on this portal?

Your feedback helps us serve you better.

USER FEEDBACK

Rating results

Satisfaction with the information provided

87ratings recorded
Very satisfied32%
28 ratings
Satisfied29%
25 ratings
Neutral30%
26 ratings
Dissatisfied0%
0 ratings
Other9%
8 ratings
Thank you for your feedback!
Visits2,172,309Total visits
Online now21
Visits today2,901

Online: active in the last 5 minutes